General planner or individual planners?

Interfaces, liability, fees · Reading time 7 minutes

DefinitionIn 60 words

The decision, in brief

A general planner takes on all design services for a scheme in one contract: architecture, structural engineering, building services and the other specialist disciplines, which it provides itself or subcontracts. With individual planners, the owner signs a separate contract with each discipline; the architect coordinates technically, but contractually the designers stand side by side. In both models, control on the owner's side remains open.

In short: the general planner sells one interface fewer and one liability more, against a premium and less choice of specialists. Individual appointments sell the free choice of the best specialists against coordination effort and divided liability. Whoever decides should know who leads the design in their organisation. If that person is missing, that is the real gap.

ComparisonSeven criteria

General planner or individual planners

No.CriterionGeneral planner · Individual planners
01ContractsGP: one design contract, one point of contact. Individual: three to eight contracts that the owner or their representative negotiates, administers and aligns.
02InterfacesGP: interfaces between architecture, structure and services sit inside the GP's office. Individual: coordination is a basic service of the architect, but without contractual authority over the specialist engineers.
03LiabilityGP: liable for its sub-planners as for its own agents, section 278 of the German Civil Code. Individual: each liable for their own work; jointly and severally for jointly caused defects, but the owner must prove who caused them.
04FeesGP: HOAI scopes of service plus a freely negotiated premium for coordination and assumption of liability. Individual: fees per contract according to the HOAI scopes, freely negotiable as reference values since 2021.
05SelectionGP: brings its own specialists; the owner rarely chooses them. Individual: free choice of the best office per discipline, by reference and capacity.
06ReplacementGP: a weak specialist is the GP's matter; the owner cannot replace them directly. Individual: each contract can be terminated on its own, a change does not hit the whole design.
07ChangesGP: change requests run through one office but are re-priced as a whole. Individual: changes per discipline, more transparent, but more alignment.
InterfacesWhere design errors arise

Why coordination decides the question

Design errors rarely arise within one discipline. They arise in between: the opening that the services need and the structure does not know about. The shaft size the architect draws that is too small for the ventilation. The slab thickness in the cost estimate that is not in the structural model. Every one of these gaps costs more on site than at the desk, and every one is a change order that no contract excludes.

The general planner moves these interfaces into its own office. That is its strongest argument. With individual appointments, coordinating and integrating the contributions of the other disciplines is a basic service of the architect in work stages 2, 3 and 5. The architect coordinates, but is not the client of the specialist engineers. If a structural engineer is late or delivers incomplete work, the architect can remind, not instruct. Only the owner can instruct, and for that the owner needs someone who reads the design stages and sees the delay before it reaches the site.

That is the project controller's role, and it is missing in both models. The general planner, too, is a contractor, not a representative. It checks its design against its fee, not against the owner's budget. What an owner's representative does in the design phase is set out in What does an owner's representative do?

LiabilityOne debtor or many

Who answers for a design error

With a general planner the position is clear: it owes a defect-free overall design and must accept responsibility for its sub-planners' fault. The owner has one party to claim against. The flip side: only one. If that party's indemnity cover is insufficient for the sum of all disciplines, the owner faces a debtor who cannot pay. The general planner's cover therefore belongs on the table before appointment, project-related and not only as an annual maximum.

With individual planners, each is liable for their own work. Where architect and structural engineer have caused a defect together, they are jointly and severally liable, and the owner can pick the more solvent one. In practice the difficulty lies earlier: the owner must prove whose work was defective. With an interface error, each points at the other. Whoever has documented the design stages and minuted the coordination meetings wins that dispute. Whoever has not often loses it regardless of the merits.

FeesHOAI as reference

What the models cost

Since the HOAI 2021, the fee tables are reference values, no longer binding minimum and maximum rates; that follows from the 2019 judgment of the Court of Justice of the European Union. The scopes of service for buildings, structural engineering and building services remain the yardstick against which offers can be measured, in both models.

The general planner charges the scopes of its disciplines and, on top, a premium for coordination, assumption of liability and the pricing risk of its sub-planners. The HOAI has no provision for this; the premium is freely negotiated. It is the price of one interface fewer, and it can only be judged with the individual fees placed alongside. That is precisely a task of owner's representation before the design is awarded.

Individual appointments save the premium and cost coordination. Whoever does not have it in-house buys it through project control: under the AHO fee table roughly three to four percent of construction cost at 15 to 20 million euros, more for smaller schemes, for all phases; project preparation and design account for 40 percent of that under the AHO booklet. What determines the fee in detail is set out in What does an owner's representative cost?

DecisionWhich model when

When the general planner is the right choice

The general planner is right for a technically complex building with a high share of building services, for an owner without in-house design leadership who does not want to buy in coordination, and for a tight programme in which alignment rounds between separate offices take too long. The condition is a general planner whose sub-planners you know, and cover that fits the project.

Individual planners are right when the quality of individual disciplines is decisive, for instance a specialised structural engineer for a demanding structure, when the owner has or appoints project control, and when the owner wants to keep the option of replacing one office without re-awarding the entire design. For residential schemes with conventional services this is the more common route.

In both cases the owner needs someone to lead the design: check design stages against budget and programme, prepare decisions, own cost planning and cost control. The general planner relieves the owner of coordinating the designers, not of leading the project.

When Solid EstateThe owner's representative who is an owner

How we support the decision

For our own schemes in project development we decide the question per project and carry the result with our own capital. For clients, before the design is awarded, we place the individual fees alongside the general planner's offer, check scopes, interface schedules and cover, and lead the design in the role of project control in Munich and Bavaria.

Frequently asked

What clients ask about this

What is a general planner?

A design office that takes on all design services for a scheme in one contract: architecture, structural engineering, building services and other specialist disciplines. Services it does not provide itself it subcontracts to sub-planners, for whom it is liable towards the owner.

General planner or general contractor: what is the difference?

The general planner designs, the general contractor builds. The general planner bundles the design contracts, the general contractor the construction contracts. Both can be appointed side by side; a design-and-build contractor combines the two in one contract. We compare the construction side in General contractor or owner's representation?

Is the general planner liable for its specialist engineers?

Yes. Sub-planners are its agents under section 278 of the German Civil Code; their fault is attributed to it. What matters is whether its professional indemnity covers the sum of all disciplines. The cover should be agreed and evidenced on a project basis.

Is a general planner more expensive?

As a rule yes, by a freely negotiated premium for coordination and assumption of liability. Whether it pays off only shows in comparison with the individual fees and with the effort that coordination would otherwise cause in the owner's organisation or with their project controller.

Is project control still needed with a general planner?

Yes. The general planner coordinates the designers among themselves; it does not lead the owner's project. Budget control, schedule responsibility, decision preparation and the review of its own fee claims remain tasks on the owner's side.

Sources: HOAI 2021, sections 34, 51, 55 with Annexes 10, 14 and 15 · CJEU, judgment of 4 July 2019, C-377/17 · German Civil Code (BGB) sections 278, 421, 634 · AHO booklet no. 9, 6th edition 2025. As of 09/2026. General information, not legal or fee advice for an individual case.

Let's talk about your project

Before the design is awarded is the moment when most costs can still be decided. We place the models side by side before you sign.

[06] Contact

Get in touch

[Address]Solid Estate GmbH
Hochstraße 7
81669 Munich, Germany

Planning a construction project, looking for a partner for your development, or would you like to learn more about our projects? We look forward to hearing from you.

We use your details solely to process this enquiry. See our privacy policy. Prefer direct contact? info@solidestate.de

Solid Estate